Develop a project schedule for the activities given. Show the start and finish date and duration of each activity.

INSTRUCTIONS TO CANDIDATES
ANSWER ALL QUESTIONS

Refer to the table below, which shows normal and crash (speeded up) activity duration and cost values for a number of activities involved in one of the work packages involved in the project.

(a) Develop a project schedule for the activities given. Show the start and finish date and duration of each activity. State the overall work package duration and show the

critical path.

(b) management require to shorten the project duration by at least 15%, to finish it earlier than originally presented. Show the crash sequence of cost against time using a suitable form of graphical representation. State the new total cost of the work package.

(c) Discuss the main sources of duration estimating data used by organizations when assembling project schedules. Demonstrate the use of one of them in this case.

Refer to table below, which shows the actual cost and schedule performance of two sections (each comprising two teams) working on one of the main computer work packages. Note the target production and cost figures given. It refers to the output figures of two sections (each comprising two teams) of IT division operatives who are working on one of the main computer work packages in the project. The figures for the operatives cover the first 6 weeks of the package. The teams are installing components at a planned rate of 1000 units per week per team over a 10-week total period. Each unit has an estimated cost of £100

(a) Comment on the performance of each team, each section and on the performance of the work package as a whole over the 6-week period. Support your comments using EVA variables such as CV/SV or CVI/SVI.

(b) Calculate estimate at completion (EAC) for each team at week 1, for Sections 1 and 2 at week 4, and for the work package as a whole for each week 1–6.

(c) Discuss the concept of estimated cost to complete (ECTC) and calculate ECTC for each section and for the work package as a whole at week 6.

(5/5)
Attachments:

Related Questions

. The fundamental operations of create, read, update, and delete (CRUD) in either Python or Java

CS 340 Milestone One Guidelines and Rubric  Overview: For this assignment, you will implement the fundamental operations of create, read, update,

. Develop a program to emulate a purchase transaction at a retail store. This  program will have two classes, a LineItem class and a Transaction class

Retail Transaction Programming Project  Project Requirements:  Develop a program to emulate a purchase transaction at a retail store. This

. The following program contains five errors. Identify the errors and fix them

7COM1028   Secure Systems Programming   Referral Coursework: Secure

. Accepts the following from a user: Item Name Item Quantity Item Price Allows the user to create a file to store the sales receipt contents

Create a GUI program that:Accepts the following from a user:Item NameItem QuantityItem PriceAllows the user to create a file to store the sales receip

. The final project will encompass developing a web service using a software stack and implementing an industry-standard interface. Regardless of whether you choose to pursue application development goals as a pure developer or as a software engineer

CS 340 Final Project Guidelines and Rubric  Overview The final project will encompass developing a web service using a software stack and impleme