The Christopher Building Project Part 1 (20 Points)
Project description
Snyder Engineering has been engaged to undertake the Christopher Building Project. Due to some unforeseen circumstances, the project owner went bankrupt and the project was sold to a new company. The originally appointed Project Manager, Bob Sachs decided to retire. The new owner has re-engaged Snyder to re-launch the Christopher Building Project. Snyder has appointed a seasoned Project Manager, Francis Lo, to lead this project.
The project schedule has been revised by the new Project Manager from the original 29-week duration to an aggressive 24-week completion. As a result, the project budget has increased by about 20% from the original $2.4M to $2.9M.
The WBS has already been established previously. Refer to Figure 1.1. Assignment for Part 1:
Develop WBS outline using the MS project 2016 or 2019, using the WBS column and Task Name
Once you have completed the above exercise you can use the information provided below to complete the preliminary schedule. Refer to Table 1.1 below.
Each work package will represent an
The project begins 18 Nov
The following holidays are observed: All Canadian (Ontario) statutory holidays in 2019 and 2020. Google “Ontario Statutory holidays” to get the
If a holiday falls on a Saturday then Friday will be given as extra day off, and if it falls on a Sunday, then Monday will be givens as a day
The project team work eight-hour a day, Monday through
Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect!
Provide the following answers:
When is the project estimated to be completed? How long will the project take?
What is the critical path(s) for the project?
Which activity has the greatest amount of slack?
Include the following printouts in Tabloid (11x17) format:
A Gantt chart, showing all the active columns
A schedule table reporting ES, LS, EF, LF, and slacks for each
Submit your MS Project file electronically on BrightSpace. Remember: Save your file for future
TABLE 1.1
Activity |
Task Name |
Duration |
Predecessors Activities |
1 |
Structural Design |
17 days |
|
2 |
Structural Steel Fabricate |
30 days |
1 |
3 |
Erect Structure |
15 days |
2 |
4 |
Building Envelope Design |
15 days |
1SS |
5 |
Install Roof |
12 days |
3, 4 |
6 |
Install Windows |
10 days |
27 |
7 |
Install Siding |
12 days |
5SS |
8 |
Install Floor Slab |
5 days |
5, 7 |
9 |
Install Mech Equipment |
20 days |
16, 3, 5, 6, 7, 8 |
10 |
Install Elec Equipment |
22 days |
21, 3, 5, 6, 7, 8 |
11 |
Install Interior Trims |
15 days |
27, 8 |
12 |
Design Mech System |
15 days |
4SS |
13 |
Solicit Mech Bids |
10 days |
12 |
14 |
Award Mech Contract |
2 days |
13 |
15 |
Fabricate Mech System |
35 days |
14 |
16 |
Deliver Mech System |
5 days |
15 |
17 |
Design Elec System |
15 days |
12SS |
18 |
Solicit Elec Bids |
10 days |
17 |
19 |
Award Electrical Contract |
2 days |
18 |
20 |
Fabricate Elec System |
35 days |
19 |
21 |
Deliver Elec System |
5 days |
20 |
22 |
Design Windows |
5 days |
4 |
23 |
Design Door Trims |
5 days |
22 |
24 |
Design Office Area |
7 days |
23 |
25 |
Solicit Arch. Bids |
10 days |
24, 23 |
26 |
Award Architectural Contract |
5 days |
25 |
27 |
Deliver Architectural Products |
38 days |
26 |
CS 340 Milestone One Guidelines and Rubric Overview: For this assignment, you will implement the fundamental operations of create, read, update,
Retail Transaction Programming Project Project Requirements: Develop a program to emulate a purchase transaction at a retail store. This
7COM1028 Secure Systems Programming Referral Coursework: Secure
Create a GUI program that:Accepts the following from a user:Item NameItem QuantityItem PriceAllows the user to create a file to store the sales receip
CS 340 Final Project Guidelines and Rubric Overview The final project will encompass developing a web service using a software stack and impleme